Permcon permeable concrete was selected for a car park extension at Tauranga Historic Village to address two key requirements – structural integrity for the parking surface and protection of an established kahikatea’s roots.
The project for Tauranga City Council, carried out by HEB Construction, included 154m² of Permcon in a Half Black colour finish within the tree protection zone.
Why Permcon was chosen
The original pavement design specified flexible pavement with an open-graded porous asphalt (OGPA) finish. However, the extent of the tree roots placed restrictions on how the pavement could be constructed.
The project arborist would not allow preloading or heavy pavement compaction over the roots, prompting consideration of a concrete solution for this area.
Permcon was chosen because it could provide structural integrity for the finished car park while allowing water and gas exchange around the roots.
Addressing the tree protection requirements
Within the tree protection zone, the pavement needed to accommodate parking while respecting the arborist’s restrictions on ground preparation.
Permcon’s permeable structure addressed the requirement for water and gas exchange, while its concrete matrix provided the structural integrity needed for the parking surface.
The result
The Historic Village installation demonstrates how Permcon can provide a site-specific pavement solution, where parking requirements must be balanced with the protection of established trees.